Nature of project:
In the context of saving energy became an extensive interference in all air duct networks in Building A of the Athens Tower (the highest building in Greece) by placing 88 Variable Air Volume damper from TROX to manage in optimum way air conditioning system to floors currently not used. Also was upgraded the existing Building Management System(BMS) of the building in order to integrate all necessary automation for the proper and full balance of air conditioning system.

Final project cost:
85.000€

Construction period:
5 months

Completion:
May 2012